FIA Formula E @ Battersea Park – for the London EPrix

SPADEOAK’S INVOLVEMENT:

SPADEOAK had two contracts with Formula E Operations Ltd;

The Advanced Civils Package – to carry out the necessary adjustments to the existing park roads to form the track.
A new car park was constructed to act as a chicane for the race but also as a permanent legacy for the park users in the future. The existing roads were repaired and resurfaced where necessary to provide a suitable track for high performance cars to race on, including kerbing and other civil engineering works.
In the process 2,096 tonnes of Asphalt was delivered by Yeoman Asphalt and laid by Spadeoak, also using 100 cu m of ready mix from London Concrete.

Track Barriers Package

To “Supply, installation, de rig and storage of walls and fences for London Race”.  Spadeoak and Charcon worked together to produce 8,500 tonnes of bespoke pre cast concrete barriers and deliver them to site to a very tight programme.
We took possession of the park and delivered and installed 7.2 km of trackside barrier and debris fencing in just 10 days.

•  Up to 75 men and staff all from Spadeoak were deployed on site each day.

•  26 items of Spadeoak plant were utilised.

•  40 Articulated Lorries full of fencing panels.

•  271 Articulated lorries of Charcon barrier  blocks.

Useful links;

Wandsworth BC press/twitter release

The ITVsport ad